Expansion of Sal-Rei Harbour in Boa vista island

The ministry of infrastructure, transport and communication of Cape Verde has awarded the contract to the contractor for the expansion of SAL REI harbour in Boa Vista Island.

The structure suffered several storms during its construction phase with the consequences of the damage areas unprotected. The already protected areas have not suffered damage ; despite these findings, the design has been redesigned because the observed intensity of storms was significantly higher than the events for which they were designed.

16.179, -22.927

The added value of CLI

In this project, CLI was involved as the ACCROPODE™ technology provider and provided technical assistance with placing drawings, advice on best practices, and onsite technical assistance.

Special features of the project

The new design has planned the implementation of cubic blocks and the placement of a specific concrete block at the foot designed by the contractor. Subsequently other storms have caused new damage on cubic blocks and foot. However very little damage has been identified on ACCROPODE™ units, showing good resilience in the face of major storms..

Hydraulic conditions

  • Design wave conditions: Hs 6.4m - Tp 21s
  • Depth of the units: -5.7 m
  • Length of the protected structure : 300 m
  • Crest level of the units : +7 m

Aspect construction

  • Number of units: 3251
  • Size of the units: 5 et 6.3 m3
  • 14 rows on the slope Transition with cubic units
Country
Cape Verde
Owner
Ministry of infrastructure, transport and communication of Cape Verde - ENAPORE
Company
SOMAGUE
Designer
Royal Haskoning
Date
2010 - 2014
Role of CLI
Sublicense contract and technical assistance for ACCROPODE™ units