Protection and rehabilitation of the Black Sea coast - Romania : an ACCROPODE™ II project

Protection and rehabilitation of the Black Sea coast - Romania 

CLI and STRABAG worked together in Romania to build an environmentally friendly breakwater, for the protection and stabilization of the Black Sea coastline.

44.5106228, 28.768328

The added value of CLI

Understanding of the Contractor’s need. Problems solving mindset applied to this specific project.

Special features of the project

To protect and rehabilitate the Romanian black sea coast, the construction of a 250m long breakwater has been undertaken. The 1 m3 ACCROPODE™ II  blocks are placed on the breakwater roundhead.

 

Hydraulic conditions

  • Length of the breakwater protected with ACCROPODE™ II blocks : 100 m

  • Max. seabed depth (toe): -3 m 

  • Top of the crest: +3 m 
     

 

Construction aspect

The breakwater was built from land. 620 ACCROPODE™ II units of 1m3 were placed using cranes.

Country
Romania
Owner
ADMINISTRIA BAZINALA DE APA DOBROGEA LITORAL
Company
STRABAG SRL
Designer
EPMC Consulting SRL
Date
2022 - 2023
Role of CLI
Sublicense contract and technical assistance for ACCROPODE™ II units