Protection and rehabilitation of the Black Sea coast - Romania : an ACCROPODE™ II project
Protection and rehabilitation of the Black Sea coast - Romania
CLI and STRABAG worked together in Romania to build an environmentally friendly breakwater, for the protection and stabilization of the Black Sea coastline.
Understanding of the Contractor’s need. Problems solving mindset applied to this specific project.
Special features of the project
To protect and rehabilitate the Romanian black sea coast, the construction of a 250m long breakwater has been undertaken. The 1 m3 ACCROPODE™ II blocks are placed on the breakwater roundhead.
Hydraulic conditions
Length of the breakwater protected with ACCROPODE™ II blocks : 100 m
Max. seabed depth (toe): -3 m
Top of the crest: +3 m
Construction aspect
The breakwater was built from land. 620 ACCROPODE™ II units of 1m3 were placed using cranes.