Khalifa Rail Port Expansion in UAE : an ACCROPODE™ I project
Khalifa Rail Port Expansion in UAE : an ACCROPODE™ I project
This reclamation platform will be protected by a breakwater build with 1.5 m3 and 2.2 m3 ACCROPODE™ I blocks.
Understanding of the Contractor’s need. Problems solving mindset applied to this specific project. |
Special features of the project
CLI provided its technical assistance and a Compliance Certificate for the entire installation of the ACCROPODE™ I blocks on the structure.
This Compliance Certificate is a guarantee of quality. The monitoring and verification of the installation is done using a 3D model of the armour made on the basis of bathymetric and photogrammetric surveys during construction.
hydraulic conditions
- Breakwater protected with ACCROPODE™ I blocks : 3.2 km
- Max. seabed depth (toe): -8.3 m
- Top of the crest: +5.2 m
Construction Aspect
The breakwater was built from land. 27 200 ACCROPODE™ I units of 1.5 m3 and 2.2 m3 were placed using cranes.