HALLANIYAT harbour

Hallaniyat island is located 200 km from the North-East of Salalah (Oman). The owner is the MOAF (Ministry of Agriculture and fisheries). GALFAR Contractor awarded a contract for the construction of the port of Hallaniyat.

17.033, 54.363

Special features of the project

The project involves two breakwaters of 700m and 100m protected with CORELOC ™ units:

  • 4 477 units of 2.0 m3
  • 2 890 units of 3.0 m3

The placement of units was performed with GPS and supervision by divers from April 2012 to December 2013.

Hydraulic conditions

  • Cumulated length of CORE-LOC™ armouring: 800 m
  • Max. seabed depth (toe): -11m
  • Top of the crest: +7.0m
  • Design wave Hs: 4.65 m

Construction aspect

  • The CORE-LOC™ units had been cast on the site.
  • CORE-LOC™ sizes: 2.0 m3 , and 3.0m3
  • 7 367 CORE-LOC™ units in total
  • Concrete quantity: 17 624m3
  • Placement performed with GPS and divers
Owner
MOAF
Company
GALFAR
Designer
DR NIK & ASSOCIATES SDN. BHD. (MALAYSIA)
Date
2012 - 2013